City of Estevan Announces Continued Progress on Downtown Revitalization Project

FOR IMMEDIATE RELEASE

City of Estevan Shares Current Project Timeline for Downtown Revitalization

Estevan, SK – May 9, 2025 — The City of Estevan is pleased to share the current project timeline for the Downtown Revitalization Project. This initiative continues to enhance the downtown core with improvements to roads, sidewalks, drainage, and streetscaping. The updated timeline reflects the latest construction phases planned for the remainder of 2025, with efforts made to minimize disruption while keeping progress on track.

 

Area Section Dates Details
1100 Block

Entire Block

Apr 30 – May 19, 2025

Channel drains and finishing work

1200 Block – Southside RBC to Midpoint Jul 2 – Jul 30, 2025

Full construction

  Midpoint to West End Jul 31 – Aug 28, 2025

Full construction

1200 Block – Northside Orpheum to Gerry Meats May 26 – Jun 24, 2025

Full construction

  Gerry Meats to BMO Jun 2 – Jul 2, 2025 Full construction
1300 Block – Both Sides Entire Block Sep 8 – Oct 6, 2025 Full construction
Streetscaping Bollards and Trees Sep 8 – Oct 6, 2025 Installed alongside 1300 block work
Final Paving & Finishing Entire Project Area Oct 7 – Oct 15, 2025 Surface paving and detail work

The City of Estevan thanks everyone for their continued patience and support as we work with our contactors to ensure timely results and continued progress for the community.

We invite the public to follow ongoing updates via the City’s website and social media channels.