Estevan, SK – May 9, 2025 — The City of Estevan is pleased to share the current project timeline for the Downtown Revitalization Project. This initiative continues to enhance the downtown core with improvements to roads, sidewalks, drainage, and streetscaping. The updated timeline reflects the latest construction phases planned for the remainder of 2025, with efforts made to minimize disruption while keeping progress on track.
| Area | Section | Dates | Details |
| 1100 Block |
Entire Block |
Apr 30 – May 19, 2025 |
Channel drains and finishing work |
| 1200 Block – Southside | RBC to Midpoint | Jul 2 – Jul 30, 2025 |
Full construction |
| Midpoint to West End | Jul 31 – Aug 28, 2025 |
Full construction |
|
| 1200 Block – Northside | Orpheum to Gerry Meats | May 26 – Jun 24, 2025 |
Full construction |
| Gerry Meats to BMO | Jun 2 – Jul 2, 2025 | Full construction | |
| 1300 Block – Both Sides | Entire Block | Sep 8 – Oct 6, 2025 | Full construction |
| Streetscaping | Bollards and Trees | Sep 8 – Oct 6, 2025 | Installed alongside 1300 block work |
| Final Paving & Finishing | Entire Project Area | Oct 7 – Oct 15, 2025 | Surface paving and detail work |
The City of Estevan thanks everyone for their continued patience and support as we work with our contactors to ensure timely results and continued progress for the community.
We invite the public to follow ongoing updates via the City’s website and social media channels.