City of Estevan Announces Continued Progress on Downtown Revitalization Project

FOR IMMEDIATE RELEASE

City of Estevan Announces Continued Progress on Downtown Revitalization Project

Estevan, SK – April 9, 2025 — The City of Estevan is pleased to provide an update on the ongoing Downtown Revitalization Project. As we enter the 2025 construction season, residents and businesses can expect visible and significant activity as the revitalization advances into its second year.

•April 22, 2025 – Mid October

April 22- Mid May
The 2025 phase of the project is scheduled to begin, with work focusing on the completion of the 1100 block, including channel drains and adjustments around key utility areas.
Mid May – Mid July
Work on the south side of the 1200 block will be carried out in two stages, starting from the bank corner and moving westward.
Early July – Mid September
Crews will transition to the north side of the 1200 block, beginning at the east corner near Gerry’s Meats and progressing westward.
Early September-Mid October
The final portion of work will involve the installation of bollards, tree planting, and the completion of surface finishes and pavement markings.

Throughout this period, all aspects of construction including sidewalk upgrades, underground infrastructure, paving, and streetscaping will be carried out in a phased manner to minimize disruptions and maintain access to businesses whenever possible.

Mayor and Council remain committed to improving the quality of life for residents while supporting a vibrant, accessible, and modern downtown. The City extends its appreciation to residents, businesses, and visitors for their continued patience and cooperation as we move forward with this transformative project.

We invite the public to follow ongoing updates via the City’s website and social media channels.

-30-

See the official media release here

Media inquiries:
Jacquelyn Massey-Rounds
j.massey@estevan.ca
(306)634-1877